Construction begins in Jade and Zetel

The end of the year season is opened! On the construction sites in the municipalities of Jade and Zetel earth is moved for road construction and foundation work.

 

A week ago work started on command of project manager Mark Schneider. In Wesermarsch county near the village of Jade workers prepare the erection of two Enercon E70 turbines with a hub height of 64m an 2.0 MW nominal power. The road construction is far proceeded. The spur is driving the poles for the foundation into the ground. The commissioning is expected to be before Christmas.

 

At the same time near the village Neuenburg (municipality of Zetel) innoVent builds an AN Bonus 2.3/93 VS wind turbine with 93 m rotor diameter. It will be next to the existing Zetel wind farm. We are especially pleased, that to the account of the hub height of 88m the strong blowing wind can be effectively transformed.

 