Windpark Grapzow / Grischow is under rapid construction

The Windpark Grapzow / Grischow in Mecklenburg-Vorpommern is rapidly approaching completion. Thanks to outstanding cooperation with local construction companies, all ten Vestas V80 turbines have been erected and made operational on schedule. And since the 140m-high wind turbines were put into operation via a provisional grid connection prior to introduction of the recently amended Renewable Energy Law (REL - German EEG) on August 1st, they remain eligible for the higher compensation scheme under Germany´s former REL. A new wind transformer station will ensure that all units are able to run at full capacity into the e.dis medium-voltage power grid as of the end of September.